Description : Civil Works, Dal Mill . Total Cost : Approx Rs 12 Crore (Excluding Cement, Steel & Reinforcement). Work Status : In Progress
ADANI WILMAR
Adani Wilmar Ltd (Saoner, Nagpur)
Description : Civil Works, Nuggets Plant. Total Cost : Approx Rs 6.13 Crore (Excluding Cement, Steel & Reinforcement). Work Status : In Progress
GIMATEX INDUSTRIES PVT LTD (CSP UNIT)
Gimatex Industries Pvt Ltd
Description : Construction Of Spinning- Unit 2 35,000 Spindal Unit, Hinganghat. Total Cost : Approx Rs 4.8 Crore (Excluding Cement, Steel & Reinforcement). Work Status : In Progress
HINGANGHAT INTEGRATED TEXTILE PARK
Hinganghat Integrated Textile Park
Description : Construction Of Factory Building (Package-II Cotton Godown 6A & 6B). Total Cost : Approx Rs 2.50 Crore. Work Status : Completed.
HINGANGHAT INTEGRATED TEXTILE PARK
Hinganghat Integrated Textile Park
Description : Construction Of Factory Building (Package-II Cotton Godown 6A & 6B). Total Cost : Approx Rs 2.50 Crore. Work Status : Completed.
GIMATEX INDUSTRIES PVT LTD (CSP UNIT)
Gimatex Industries Pvt Ltd (CSP Unit)
Description : Construction Of Factory Building CSP Warehouse. Total Cost : Approx Rs 2 Crore. (Excluding Cement, Steel & Reinforcement) Work Status : Completed.
ADANI WILMAR
Adani Wilmar (Nimrani, Indore)
Description : Wheat Flour Mill & Misc. Work. Total Cost : Approx Rs 1.55 Crore (Excluding Cement, Steel & Reinforcement). Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Dongri Buzurg Mines)
Description : Construction Of Cement Concrete Platform & Extension of Rail Siding Platform. Total Cost : Approx Rs 4 Crore. Work Status : Completed.
VISHVARAJ INFRASTRUCTURE LTD
Vishvaraj Infrastructure Ltd (Nagpur)
Description : Construction Of Sewerage Treatment Plant (Wet Well Tank, C-Tech Basin, Chlorination Tank, Sludge Bed, Dewatering Unit). Total Cost : Approx Rs 4 Crore. Work Status : Completed.
TATA CONSULTANCY SERVICES
Tata Consultancy Services, Phase II (TPL) (Mihan, Nagpur)
Description : Initial Development Center. Total Cost : Approx Rs 2 crore. Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Mansar Mines)
Description : Construction Of Cement Road, Retaining Wall. Total Cost : Approx Rs 3.99 Crore. Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Gumgaon Mines)
Description : Construction Of Sand Stowing Plant (1 Lakh Capacity), RCC Water Tank, GI Sheet Shed, Zero Level Platform at vertical shaft, cement concrete road at industrial area premises & road side cement concrete drain . Total Cost : Approx Rs 1.40 Crore. Work Status : Completed.
HINGANGHAT INTEGRATED TEXTILE PARK
Hinganghat Integrated Textile Park
Description : Construction Of Common Facility Building (Admin Block, Lab, Canteen), Boundary Wall & Main Gate. Total Cost : Approx Rs 5.85 Crore. Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Mansar Mines)
Description : Construction Of Surface Infrastructure Building & 2nd vertical Shaft. Total Cost : Approx Rs 2.60 Crore. Work Status : Completed.
ADANI WILMAR
Adani Wilmar (Vidisha)
Description : Construction Of Boundary Wall & Misc. Work. Total Cost : Approx Rs 1.35 Crore (Excluding of Steel
& Cement). Work Status : Completed.
DECATHLON SPORTS INDIA PVT LTD.
Decathlon Sports India Pvt Ltd. (Raipur)
Description : Sales Area Building,
Admin Block, Play Ground Area,
Structure Work, Road Work,
Sewerage Treatment Plant,
VD Flooring. Total Cost : Approx Rs 2.65 Crore. Work Status : Completed.
SHRI BHAGIRATH TEXTILE LTD.
Shri Bhagirath Textile Ltd. (Nagpur)
Description : Power House, CEO Bungalow, Residential Quarters,
Dormitory, Material Storage
Shed. Total Cost : Approx Rs 4.58 Crore (Excluding of Steel
& Cement). Work Status : Completed
TATA PROJECTS LTD.
Tata Projects Ltd. (Umred, Nagpur)
Description : Tower Manufacturing Unit, Foundations,
Galvanizing Shed, Fabrication
Shed Yard, Drains, Internal
Roads, Motorized Gates,
Meter Rooms, Security
Cabins, Boundary Walls. Total Cost : Approx Rs 2.5 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
GAMMON INDIA
Gammon India Ltd. (Deoli, Wardha)
Description : TMU Unit & Test Bed. Total Cost : Approx 7.5 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
ABB
ABB Vadodara (Wardha)
Description : Construction Of 765 KV Switchyard, RCC
Road, Drain, Foundation & Yard at DEOLI Powergrid.
Total Cost : Approx Rs 6 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Gumgaon Mines)
Description : Construction Of Decentralised Sewerage Treatment Plant, Vertical Shaft, Cement Concrete Platform. Total Cost : Approx Rs 1.25 Crore. Work Status : Completed.
GMR
GMR (EMCO, Chandrapur)
Description : Sewerage Treatment Plant, Coal Handling Plant, Stacker,
Drains and Misc. Work. Total Cost : Approx Rs 1.5 Crore (Excluding of Steel
& Cement). Work Status : Completed.
ERA T & D ERA BUILDING SYSTEMS LTD
Era T&D (Umred) Era Building Systems Ltd. (Umred)
Description : Construction of Tower Manufacturing Unit, Pre Engineered Building Plant, Foundation & Trimix Floor. Total Cost : Approx 6.6 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
INDIABULLS INFRA
Indiabulls Infra (Amravati)
Description : Rack Foundation At Indiabulls
Power Plant. Total Cost : Approx Rs 1.5 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
ABB
ABB Calcutta (Indiabulls Power Plant, Amravati)
Description : Construction of Switch Yard, RCC Road, Drain
For 400/220 KV
Substation. Total Cost : Approx Rs 2.5 crore
(Excluding of Steel
& Cement). Work Status : Completed.
SUGUNA GROUP
Sugana Group (Hinganghat)
Description : Effluent Treatment Plant & Refinery Foundations. Total Cost : Approx Rs 1 Crore
(Excluding of Steel
& Cement). Work Status : Completed.
ADANI WILMAR
Adani Wilmar (Nagpur & Chindwara)
Description : RCC Road, Compound Wall & Other Building Work. Total Cost : Approx Rs 1.5 Crore (Excluding of Steel
& Cement). Work Status : Completed.
MANGANESE ORE (I) LTD
Manganese Ore (I) Ltd (Kandri Mines)
Description : Construction Of Retaining Wall For Railway Siding Platform & Vehicle Shed. Total Cost : Approx Rs 3.10 Crore. Work Status : Completed.